Theatre Project Improvements

 
01/06/2006 3 Phase Power to the Venue, New Power Cable supply to the Building, 3 x 60 000 BTU Air Conditioners   Picture
The time had come to purchase and install air cons before summer, but you need 3 phase power to run them ...
 
01/01/2005 Repainted the Building Exterior & Interior  
We needed to look fresh, this was soon to be our 5 year anniversary.
 
15/01/2004 New Lights and Smoke Machine Picture
Up to now we had been hiring lights and we needed more in the venue, we wanted to run 20 lighting channels.
 
15/01/2003 Installed new Fans, New 3 Phase DB Board   Picture
The DB board was not originally a priority, but when drawing power to run the lighting for the theatre, we just we running a bit thin.
 
30/10/2002 New Awning and Concrete for Walkways Detail Picture
With Durban rain, one just never knows, a wet audience is not fun...
 
30/06/2001 Toilet Alterations for Patrons & Dressing Room Picture
When we opened The Rhumbelow the toilet facilities where not adequate for an audience and there was no dressing room, so I got my builder friend to "JUST DO IT"..... I said "I will pay you after the show", and we did.
 
       
We are in the process of updating this page.